Nvidia halves the OpenAI backstop, and the buildout's credit now moves with its share price
The guarantee that made a $500bn Ohio campus financeable is under half its old size, three weeks after the market marked Nvidia down 5% for offering it.
The Product Desk
What happened
- Under new proposed terms, Nvidia would initially backstop only half of the 10GW OpenAI project and would decide about the rest later; Anissa Gardizy reported the cut for The Wall Street Journal on 14 August.
- The earlier arrangement was a $250bn Nvidia backstop of the OpenAI project.
- The Journal says Nvidia made the change to address investor concerns about its own risk exposure.
- The project would be the largest data centre project announced anywhere.
- OpenAI has no investment-grade credit rating, so lenders were being asked to price the debt against Nvidia's instead.
Why it matters
Nvidia has proposed initially backstopping only half of its 10GW data centre project with OpenAI, down from a guarantee of $250bn covering the whole thing, and deciding about the remainder later, according to Anissa Gardizy's 14 August report for the Wall Street Journal [4][5]. The Journal says the change was made to address investor concerns about Nvidia's own risk exposure [6], which states plainly what the lenders already knew: the debt behind the largest data centre project announced anywhere is priced against one chipmaker's balance sheet [1][7].
The structure explains the size of the promise. OpenAI has no investment-grade credit rating, so lenders were being asked to price the debt against Nvidia's instead [7]. Total project cost passes $500bn once the silicon is counted, and a first phase of roughly 800MW is due for completion in 2028 [2][3], about 8% of the announced capacity [30]. SB Energy, a SoftBank subsidiary, is developing the site [8], and Reuters reported the same evening that OpenAI is still negotiating a binding lease for the full 10GW [9].
This desk reported the $250bn backstop on 27 July, the day after the Journal broke it, when it would have been the largest financial guarantee ever discussed between two private companies [10][11]. Nvidia shares fell 5% after that first report [16], and the guarantee is now under half the size [12]. Nothing about the Ohio campus changed in three weeks [13]. At $250bn the promise covered roughly half the project cost; under the new terms it covers less than a quarter [31]. It is also the second trim of the same partnership: a September agreement covering at least 10GW, with Nvidia investing up to $100bn, stalled after some inside Nvidia expressed doubts [17].
What remains is substantial but softer. A separate agreement to finance OpenAI's chip purchases could total $350bn across the full project, money Nvidia would help arrange rather than guarantee outright [14]. Goldman Sachs is advising SB Energy and Morgan Stanley is advising Nvidia [15]. The power is the uncontested part: the US government controls it and Japan funds it separately under a recent trade deal [18].
On the same day, Nvidia filed a 13F disclosing its US equity holdings for the quarter ended 30 June [19]. Intel was the larger position at 214.8 million shares worth about $30bn, built from a $5bn investment and worth roughly $9.5bn a quarter earlier [20][21], a paper gain of about $25bn [32] on a foundry recovery Nvidia bought into rather than engineered [22]. SpaceX was second, at 122.8 million Class A shares worth roughly $21bn [23]. Both have since fallen. SpaceX closed at $140 on Friday against $170.86 at the end of June, down about 18% [24][33], leaving that stake near $17.2bn and Intel's near $22bn [25], or roughly $12bn of value gone in six weeks on paper [26].
That is the link between the two filings. The balance sheet tolerance that makes a 10GW lease financeable is itself marked to markets that reprice weekly, and both of the big holdings buy Nvidia chips [27]; Musk has said SpaceX will use Nvidia silicon exclusively and expects a significant allocation of Vera Rubin GPUs next year [28].
Watch whether the deal is signed, which the Journal said could happen as soon as this weekend [29], and on what terms the unguaranteed half is settled later. Watch the binding lease for the full 10GW [9]. And note that the provenance of the SpaceX stake is disputed: CNBC traces it to a $10bn Nvidia investment in xAI in January, part of a $20bn round, while Bloomberg reports as much as $2bn put into xAI during 2025 through a special purpose vehicle mixing equity and debt to buy Nvidia processors [34][35]. SpaceX acquired xAI in February at $1.25trn, which is how an xAI position became a SpaceX position [36].
Clarity's read
What the record supports and how the coverage leans. The claims behind it follow.
Reality
- Evidence60
- Adoption
- Not scored
- Hype gap+20
- Incentives65
- Confidence58
Claim ledger
Ranked by verification strength, evidence, and original report placement.
- [1]
The project would be the largest data centre project announced anywhere.
- [2]
The total project cost passes $500bn once the silicon is counted.
- [3]
A first phase of roughly 800MW is due for completion in 2028.
- [4]
Under new proposed terms, Nvidia would initially backstop only half of the 10GW OpenAI project and would decide about the rest later; Anissa Gardizy reported the cut for The Wall Street Journal on 14 August.
- [5]
The earlier arrangement was a $250bn Nvidia backstop of the OpenAI project.
- [6]
The Journal says Nvidia made the change to address investor concerns about its own risk exposure.
- [7]
OpenAI has no investment-grade credit rating, so lenders were being asked to price the debt against Nvidia's instead.
- [8]
SB Energy, a SoftBank subsidiary, is developing the site.
- [9]
Reuters carried the story the same evening and reported that OpenAI is still negotiating a binding lease for the full 10GW.
- [10]
The publication reported the $250bn backstop on 27 July, the day after the Journal broke it.
- [11]
The $250bn backstop would have been the largest financial guarantee ever discussed between two private companies.
- [12]
The guarantee is now under half the size of the original.
- [13]
Nothing about the Ohio campus itself changed in the three weeks between the two reports.
- [14]
A separate agreement to finance OpenAI's chip purchases could total $350bn across the full project, money Nvidia would help arrange rather than guarantee outright.
- [15]
Goldman Sachs is advising SB Energy and Morgan Stanley is advising Nvidia.
- [16]
Nvidia shares fell 5% after the first Journal report of the backstop.
- [17]
Nvidia and OpenAI announced an agreement last September covering at least 10GW, with Nvidia investing up to $100bn; that deal stalled after some inside Nvidia expressed doubts, making this the second trim of the same partnership.
- [18]
The US government controls the power for the project, and Japan funds it separately under a recent trade deal.
- [19]
Nvidia disclosed its US equity holdings for the quarter ended 30 June in a 13F filing on 14 August.
- [20]
Nvidia held 214.8 million Intel shares worth about $30bn at the end of June, built from an investment of $5bn.
- [21]
A quarter earlier the same Intel stake was worth roughly $9.5bn.
- [22]
Intel has roughly quintupled over 12 months on the strength of its foundry turnaround, and Nvidia's $5bn went in less than a year ago; Nvidia bought into a recovery that then happened rather than engineering one.
- [23]
Nvidia's SpaceX holding was 122.8 million Class A shares worth roughly $21bn, its second-largest position.
- [24]
SpaceX closed at $140 on Friday, down from $170.86 at the end of June.
- [25]
At Friday's price the SpaceX stake is worth about $17.2bn, and the Intel stake has fallen to roughly $22bn.
- [26]
Roughly $12bn of value has gone in six weeks, on paper, across the two positions.
- [27]
Both of Nvidia's big holdings buy Nvidia chips.
- [28]
Musk has said SpaceX will use Nvidia silicon exclusively and expects a significant allocation of Vera Rubin GPUs next year.
- [29]
A deal could be signed as soon as this weekend.
- [30]
A first phase of roughly 800MW is about 8% of the announced 10GW capacity.
- [31]
At $250bn the guarantee covered roughly half of the project's $500bn-plus cost; at under half that size it covers less than a quarter.
- [32]
The Intel stake showed a paper gain of about $25bn against the $5bn invested.
- [33]
SpaceX's move from $170.86 to $140 is a decline of about 18%.
- [34]
CNBC says the SpaceX shares came from Nvidia's $10bn investment in xAI in January, as part of a $20bn round.
- [35]
Bloomberg says Nvidia put as much as $2bn into xAI during 2025, through a financing that mixed equity and debt inside a special purpose vehicle built to buy its processors.
- [36]
SpaceX acquired xAI in February at $1.25trn, which is how an xAI position became a SpaceX position.
Sources
2 independent publishers whose own reporting we read for this story.
- interestingengineering.comNvidia cuts $130B+ from OpenAI’s 10GW Ohio campus backing amid risk concerns: Reports
1 article · August 14, 2026
- thenextweb.comNvidia halved its $250bn promise to OpenAI. Then it showed investors what it owns
1 article · August 15, 2026