Project Jupiter

A 2.45 gigawatt Oracle data centre in Doña Ana County, New Mexico, described as a centrepiece of Oracle's $300bn computing deal with OpenAI.

Known aliases

  • Project Jupiter campus
  • Project Jupiter data center

Current stories

investConfirmed2 publishers

Trucked gas for Oracle's Project Jupiter would empty a trailer every 40 minutes per 100 MW

Oracle is trucking compressed gas to AI data centers with late pipelines and weighing the same fix for its 2.45 GW Project Jupiter, Bloomberg reported. One analyst puts trucked gas at about four times the cost of pipeline supply, though at Jupiter's scale the number of trailers an hour is the tighter limit.

Publishers:qz.com thenextweb.com

Reality

Evidence55
Adoption40
Hype gap+5
Incentives50
Confidence60
investConfirmed10 publishers

Oracle's force majeure notice on Jupiter tests who pays when AI campuses run late

Oracle issued a force majeure notice on Blue Owl's Jupiter campus, whose reported $18bn of bank loans already trade below 90 cents on the dollar. Lenders who priced Oracle's credit now also have to price who pays when the power arrives late.

Perspective Coverage

12 publishers
Builder
Builder 4%
Operator
Operator 22%
Investor
Investor 74%

Reality

Evidence60
Adoption20
Hype gap+25
Incentives65
Confidence55
productConfirmed4 publishers

Oracle hedges Project Jupiter's 2028 date with a force majeure notice over its gas supply

Oracle sent Project Jupiter's developer a force majeure notice that lets it delay payments if the New Mexico campus misses its 2028 target. The site's gas pipeline and air permit are both still pending, so capacity plans built on that date need a fallback.

Perspective Coverage

6 publishers
Builder
Builder 13%
Operator
Operator 39%
Investor
Investor 48%

Reality

Evidence62
Adoption
Not scored
Hype gap+15
Incentives68
Confidence64
investOne report1 publisher

Each point on the 10-year yield would add $41 billion a year to AI's $4.1 trillion debt bill

Ten-year Treasury yields near 5.17%, the highest since 2007, raise the cost of the $4.1 trillion in AI debt JPMorgan expects through 2030. Oracle fell 7% this week as CoreWeave rose almost 8%, a split that follows Oracle's campus news more than rate exposure.

Publishers:cnbc.com

Reality

Evidence58
Adoption
Not scored
Hype gap+35
Incentives55
Confidence52
leadershipConfirmed3 publishers

With a force majeure notice, Oracle hedges against Project Jupiter running late

Oracle shares fell more than 6% on Thursday after it sent a force majeure notice to Blue Owl over Project Jupiter, its New Mexico AI data center. The notice protects Oracle's cash if the site runs late and makes its 2028 date the one lenders and investors now watch.

Publishers:businessinsider.com forbes.com.au santafenewmexican.com

Perspective Coverage

3 publishers
Builder
Builder 7%
Operator
Operator 40%
Investor
Investor 53%

Reality

Evidence62
Adoption
Not scored
Hype gap+20
Incentives60
Confidence60
buildOne report1 publisher

Oracle's force majeure notice puts power on Project Jupiter's critical path

Oracle invoked force majeure on Project Jupiter, a New Mexico AI campus for OpenAI now expected to run about a year late. The delay postpones the higher post-completion return on Blue Owl's roughly $3 billion of equity.

Reality

Evidence60
Adoption
Not scored
Hype gap+15
Incentives65
Confidence55
leadershipOne report1 publisher

New Mexico's high court hands Project Jupiter's permit fight back to state regulators

The extraordinary-relief route two environmental groups chose bought them about a month of paused proceedings at New Mexico's air and water agencies, and it ends with the air permit still undecided before a hearing officer the state has yet to name.

Publishers:santafenewmexican.com

Reality

Evidence74
Adoption58
Hype gap+5
Incentives78
Confidence68
investOne report1 publisher

Disclosed financings cover about a quarter of Oracle's $300bn OpenAI commitment

Michigan's package is $16.3bn anchored by PIMCO, Texas and Wisconsin about $38bn, New Mexico $18bn. Against a target of up to 10 gigawatts, the named money works out at roughly $7.2bn per gigawatt. The suppliers bill on megawatts energised.

Reality

Evidence30
Adoption55
Hype gap+34
Incentives65
Confidence38
productOne report1 publisher

Oracle asks New Mexico developers for 2GW of whatever comes online soonest

The RFP takes solar, wind or geothermal and scores bids on delivery timing and project maturity. That ranking tells you Project Jupiter needs matched megawatt-hours by a date more than it needs a preferred fuel.

Reality

Evidence50
Adoption35
Hype gap+34
Incentives74
Confidence57
investOne report1 publisher

Water permits and county races now set the pace of a $700bn data center build

Oracle, Meta, Google, Amazon and Microsoft plan more than $700bn of US data centers this year, roughly $58bn a month, and against that run rate a repealed state tax break costs less than two quarters of permitting delay.

Publishers:ap.org

Reality

Evidence58
Adoption71
Hype gap+16
Incentives66
Confidence61
investOne report1 publisher

In Cass County, Nebraska, the AI buildout's scarce input is not land but permission

Farmers and the Sierra Club packed a firehouse in a village of 275. The county then paused data center development for a year, and no acreage premium undoes that.

Publishers:fortune.com

Reality

Evidence52
Adoption22
Hype gap+18
Incentives72
Confidence48
productOne report1 publisher

Siting Is Now a Schedule Risk: 75 Data Centre Projects, $130bn, One Quarter

Local opposition stalled at least 75 projects worth about $130bn in three months, according to Bloomberg. That belongs in the capacity plan, not the comms plan.

Publishers:thenextweb.com

Reality

Evidence54
Adoption71
Hype gap+14
Incentives66
Confidence52