Oracle hedges Project Jupiter's 2028 date with a force majeure notice over its gas supply

Oracle sent Project Jupiter's developer a force majeure notice that lets it delay payments if the New Mexico campus misses its 2028 target. The site's gas pipeline and air permit are both still pending, so capacity plans built on that date need a fallback.

The Product Desk

Send a correction

Illustration accompanying Oracle hedges Project Jupiter's 2028 date with a force majeure notice over its gas supply
Generated illustration

What happened

  • Oracle sent a force majeure notice to the Blue Owl subsidiary building Project Jupiter, a data center campus under construction in New Mexico, Bloomberg reported.
  • A gas pipeline that was due to reach the site this summer is now delayed until next February because it failed to get permits, and the developer has proposed a different route.
  • Oracle told CNBC that Project Jupiter remains on its planned schedule.
  • Oracle shares fell more than 3% in regular trading in the hours after the report.

Why it matters

  • What doesn't add up contradiction Planners have to weigh Oracle's public schedule against a contract step that only comes into play if the schedule fails, and the contract step is the one with money attached.
  • Who's exposed exposure Blue Owl's construction unit carries the timing risk: if the gas supply or permits run late, Oracle's scheduled payments to it can slide too.
  • What it costs cost A slip could push back when Oracle books part of its revenue backlog, which KeyBanc's Jackson Ader says is what worries investors about the notice.
  • What it limits constraint Opposition from residents and environmental groups has made the project a midterm issue, so the outstanding permits are political decisions that Oracle's spending cannot speed up.

Picture a platform lead whose 2028 capacity plan counts on Oracle's New Mexico campus. They now have two Oracle signals to square. One is the company's statement: "We are fully committed to New Mexico and confident in our path forward" [6]. The other is a contract step that only comes into play if that confidence turns out to be wrong [1].

The notice keeps Oracle as the site's main tenant and lets it push back scheduled payments if the campus is not online by its 2028 target [1]. It changes when money moves. Blue Owl told Bloomberg that "this notice does not change the financial commitments to this multi-year project" [8].

The date depends on fuel. Project Jupiter is expected to deliver 2.45 gigawatts of computing power from gas-fed fuel cells supplied by Bloom Energy, so the gas supply has to be in place before the campus can run [5][3]. The pipeline is one open item. The other is a separate air-quality permit for the fuel-cell system, which New Mexico's environment department has not yet decided [11].

Energy triggered this notice. Oracle's cash figures suggest why it wanted the right to pay later. The company spent $28.5 billion on capital expenditures in its fiscal first quarter, about 3.4 times the $8.5 billion of a year earlier [12][17]. Free cash flow for the quarter was negative $5 billion [13]. "Oracle is in the most tenuous of cash positions of all the major hyperscalers," KeyBanc analyst Jackson Ader told Barron's [15]. "These types of issues might spread, but Oracle feels it more acutely than its larger, more cash rich peers," he said [16].

At this site, power sets the timetable and money drives Oracle's response. The evidence covers one campus with one fuel plan. Ader's "might spread" is a forecast, and the sources do not show power limiting AI cloud capacity across the industry.

Two facts sort any capacity commitment dated two or more years out. One is whether the power source is permitted and connected today. The other is whether the provider has given itself a contractual way to be late. A permitted, unhedged commitment can be planned on its date. Permitted and hedged, or unpermitted and unhedged, means keeping the date with a named fallback region. Unpermitted and hedged means treating the vendor's date as the earliest case and building the plan around a later one.

Project Jupiter is in that last box: its pipeline route and air permit are unresolved, and the force majeure notice has already gone out [7][11][1]. For teams that depend on it, I would plan for the slip. The cost is paying to hold capacity elsewhere that may sit idle if both permits clear on time.

What to watch

  • New Mexico's environment department ruling on the fuel-cell air-quality permit, due before November 23.
  • Whether regulators accept the developer's proposed new pipeline route in time to hold the February gas date.
  • Whether other hyperscalers' data center developers receive similar notices, as Ader says these issues might spread.

Clarity's read

What the record supports and how the coverage leans. The claims behind it follow.

Reality

Evidence62
Adoption
Not scored
Hype gap+15
Incentives68
Confidence64

Perspective Coverage

6 publishers
Builder
Builder 13%
Operator
Operator 39%
Investor
Investor 48%
Why these scores

Claim ledger

Ranked by verification strength, evidence, and original report placement.

  1. [1]

    Oracle is not trying to back away from the deal it signed to become the facility's main tenant; the notice lets it delay scheduled payments if the facility does not come online by its slated 2028 target date.

    Reported Supported Source: SiliconANGLEView cited source
  2. [2]

    Oracle sent a notice of force majeure to the developer of Project Jupiter, a data center campus under construction in New Mexico, according to Bloomberg. The developer is a Blue Owl Capital subsidiary responsible for construction, and it received the notice.

    Reported Supported Source: SiliconANGLE, citing BloombergView cited source
  3. [3]

    The campus is set to run on gas-powered fuel cells supplied by Bloom Energy, so the site requires a reliable gas supply.

    Reported Supported Source: SiliconANGLEView cited source
  4. [4]

    "Project Jupiter remains on our planned schedule," Oracle said in a statement to CNBC.

    Reported Supported Source: Oracle statement to CNBC, via SiliconANGLEView cited source
  5. [5]

    The campus is expected to generate 2.45 gigawatts of computing power when it comes online.

    Reported Supported Source: SiliconANGLEView cited source
  6. [6]

    "We are fully committed to New Mexico and confident in our path forward."

    Reported Supported Source: Oracle statement to CNBC, via SiliconANGLEView cited source
  7. [7]

    A pipeline intended to supply gas to the facility was meant to come online earlier this summer but has been delayed until February next year after failing to receive the necessary permits from regulators; the developer has reportedly proposed a different route.

    Reported Supported Source: SiliconANGLE, citing BloombergView cited source
  8. [8]

    Blue Owl told Bloomberg that "this notice does not change the financial commitments to this multi-year project."

    Reported Supported Source: Blue Owl Capital to Bloomberg, via SiliconANGLEView cited source
  9. [9]

    New Mexico residents have strongly opposed the project, with support from environmental groups, and it has become a major political issue ahead of the midterm elections.

    Reported Supported Source: SiliconANGLEView cited source
  10. [10]

    Oracle's stock fell more than 3% during regular trading in the hours following the report.

    Reported Supported Source: SiliconANGLEView cited source
  11. [11]

    The facility is awaiting a separate air-quality permit for its fuel-cell power system; New Mexico's environmental department is due to decide before a Nov. 23 deadline.

    Reported Supported Source: SiliconANGLEView cited source
  12. [12]

    Oracle said it spent $28.5 billion on capital expenditures in its fiscal first quarter, up from $8.5 billion in the same period a year earlier.

    Reported Supported Source: Oracle earnings report, via SiliconANGLEView cited source
  13. [13]

    Oracle reported negative free cash flow of $5 billion in the quarter.

    Reported Supported Source: Oracle earnings report, via SiliconANGLEView cited source
  14. [14]

    KeyBanc analyst Jackson Ader told Barron's that investors are concerned the notice could mean Oracle has to wait longer to recognize some of the billions of dollars in its revenue backlog.

    Reported Supported Source: Jackson Ader, KeyBanc, to Barron's, via SiliconANGLEView cited source
  15. [15]

    "Oracle is in the most tenuous of cash positions of all the major hyperscalers."

    Reported Supported Source: Jackson Ader, KeyBanc, to Barron's, via SiliconANGLEView cited source
  16. [16]

    "These types of issues might spread, but Oracle feels it more acutely than its larger, more cash rich peers."

    Reported Supported Source: Jackson Ader, KeyBanc, to Barron's, via SiliconANGLEView cited source
  17. [17]

    Oracle's fiscal first-quarter capital expenditure was about 3.4 times the level of a year earlier.

    Derived Supported

Sources

4 independent publishers whose own reporting we read for this story.

  1. datacenterdynamics.com

    1 article · September 24, 2026

    Oracle issues force majeure notice to Blue Owl following series of setbacks at Project Jupiter data center campus – report
  2. Oracle cites ‘force majeure’ to shield itself on data centre | Financial Post
  3. morningbrew.com

    1 article · September 24, 2026

    Oracle warns it might not pay data center lease
  4. siliconangle.com

    2 articles · September 24, 2026

    Oracle issues ‘force majeure’ notice to developer of New Mexico data center over energy delays
  5. techcrunch.com

    2 articles · September 24, 2026

    Oracle sends force majeure notice on its New Mexico Stargate data center
  6. thenextweb.com

    1 article · September 24, 2026

    Oracle cites force majeure over New Mexico data centre, Bloomberg reports