Skip to content

Invest Independently confirmed2 publishers 3 min read Published

Goldman's 'largely unchanged' data-center forecast cuts 2027 capacity additions by more than a quarter

Goldman Sachs calls its US data-center outlook through 2027 largely unchanged, yet its figures cut 2027 capacity additions to 26 GW from 36 GW. The bank says local opposition has had limited effect on growth so far, a judgement the November 3 midterms will test.

The Investor · Invest desk

Send a correction

Illustration accompanying Goldman's 'largely unchanged' data-center forecast cuts 2027 capacity additions by more than a quarter
Generated illustration

What happened

  • Goldman projects US data-center power demand rising 38% in both 2026 and 2027, an extra 12 GW and then 17 GW.
  • Its May forecast had demand climbing from 31 GW in 2025 to 41 GW in 2026 and then to 66 GW in 2027.
  • Only 14% of Americans in a June Reuters/Ipsos poll would support a data center built in their community for big tech firms' AI projects.

Why it matters

  • What doesn't add up contradiction Goldman's 'largely unchanged' holds only for the end-2027 total, about 5% below May's 95 GW, while the path underneath it now loads more of the build into 2026.
  • Who has to decide decision Anyone who sized 2027 power purchases or equipment orders off May's steep path is now working to a 2027 demand step of 17 GW, 8 GW less than the 25 GW May implied.
  • Who's exposed exposure Goldman's case against the opposition rests on a supply pipeline running through 2027, so the evidence it used to discount local resistance does not cover projects dated after that.

Before the October note [1], Goldman's figures put US data-center capacity at 59 GW at the end of 2026 and roughly 95 GW a year later [13][10]. Moving those to 64 GW and 90 GW [3] shrinks the capacity added during 2027 from 36 GW to 26 GW, a cut of about 28% to a single year's build [15]. The bank described the same numbers this way. "While US data center development faces increasing political and community opposition, project data and our updated capacity estimates suggest that the US data center growth outlook through 2027 remains largely unchanged," Goldman said [4].

Demand was reshaped the same way, into two even 38% years [2]. The May path of 31 GW, 41 GW and 66 GW [11] meant growth of about 32% in 2026 and 61% in 2027 [17]. The new 12 GW for 2026 is 38% of about 31.6 GW, so the 2025 base barely moved. Adding 12 GW and then 17 GW to that base gives roughly 61 GW of demand in 2027, about 5 GW below May [18].

Projects arriving early would explain part of the capacity move. Pure timing would have left the end-2027 total at 95 GW, though, so it covers at most 5 GW of the 10 GW cut, and the other 5 GW drops out of the two-year forecast [16]. Another possibility is that opposition is starting to reach later-dated projects. In Crypto Briefing's account, Goldman concludes that resistance has had limited effect on growth so far [8], and a cut to the later year is where an early effect would show first. Or the cause is something else. The reports do not say what drove the cut, and they do not identify electricity supply as the limit on the build.

Goldman's argument, as Crypto Briefing summarised the note, is that AI infrastructure spending by large technology firms will likely offset permitting and political barriers, with a near-term supply pipeline behind it [14]. The evidence the bank cites is project data [4]. "Public sentiment has also turned more negative," Goldman said [5]. About a third of Americans approve of the pace of construction, according to a June Reuters/Ipsos poll [6], and the objections center on electricity demand, utility costs and other local impacts [9]. The midterms are on November 3, and CNA's report calls the backlash a political challenge for Republicans [12].

I'd expect the lost 5 GW to be where opposition shows up first, because it falls in the year furthest from the near-term pipeline Goldman leans on [16][14]. The counter-case is the bank's own: its project data show the outlook holding, and it expects spending to outrun the barriers [4][14]. A later Goldman revision that restores the 2027 figure, or attributes the cut to equipment or power, would show that expectation to be wrong.

What to watch

  • The November 3 midterms and any local moratoria or permit refusals that land on hyperscaler projects scheduled for 2027.
  • Whether US capacity actually reaches Goldman's 64 GW by end-2026; a shortfall would mean the 2026 raise was not projects arriving early.

Information, not investment advice. This story is general information about companies and markets, drawn from cited reporting. It is not a recommendation to buy, sell or hold any security; check the cited sources before acting.

Clarity's read

What the record supports and how the coverage leans. The claims behind it follow.

Reality

Evidence60
Adoption
Not scored
Hype gap+25
Incentives
Not scored
Confidence58

Perspective Coverage

3 publishers
Builder
Builder 10%
Operator
Operator 33%
Investor
Investor 57%
Why these scores

Claim ledger

Ranked by verification strength, evidence, and original report placement.

  1. [1]

    Goldman Sachs issued a client note dated October 4-5, 2026 on US data-center growth.

    Reported Supported Source: Crypto Briefing report of Goldman Sachs noteView cited source
  2. [2]

    Goldman forecast US data-center power demand to grow 38% or 12 GW in 2026 and 38% or 17 GW in 2027.

    Reported Supported Source: Goldman Sachs note, as reported by CNAView cited source
  3. [3]

    Goldman raised its 2026 year-end US data-center capacity forecast by 5 GW to 64 GW and reduced its 2027 year-end forecast by 5 GW to 90 GW.

    Reported Supported Source: Goldman Sachs note, as reported by CNAView cited source
  4. [4]

    "While US data center development faces increasing political and community opposition, project data and our updated capacity estimates suggest that the US data center growth outlook through 2027 remains largely unchanged,"

    Reported Supported Source: Goldman Sachs, quoted by CNAView cited source
  5. [5]

    "Public sentiment has also turned more negative,"

    Reported Supported Source: Goldman Sachs, quoted by CNAView cited source
  6. [6]

    Just a third of Americans approve of the pace of data-center construction in the US, according to a June Reuters/Ipsos poll.

    Reported Supported Source: Reuters/Ipsos poll, as reported by CNAView cited source
  7. [7]

    Only 14% of respondents would support a data center being built in their community to support AI projects for technology firms such as Meta, Alphabet, Amazon, Microsoft and xAI, the June Reuters/Ipsos poll showed.

    Reported Supported Source: Reuters/Ipsos poll, as reported by CNAView cited source
  8. [8]

    Goldman's note acknowledges opposition is rising and concludes that this resistance has had limited effect on growth trajectories so far.

    Reported Supported Source: Crypto Briefing summary of Goldman noteView cited source
  9. [9]

    Data centers have drawn opposition in communities nationwide over concerns about electricity demand, utility costs and other local impacts.

    Reported Supported Source: CNAView cited source
  10. [10]

    Goldman's May 2026 forecast anticipated US data-center capacity of roughly 95 GW by the end of 2027.

    Reported Supported Source: Crypto BriefingView cited source
  11. [11]

    Goldman's May 2026 forecast had US data-center power demand climbing from 31 GW in 2025 to 41 GW in 2026, then to 66 GW in 2027.

    Reported Supported Source: Crypto BriefingView cited source
  12. [12]

    The backlash poses a political challenge for Republicans heading into the US midterm elections on November 3.

    Reported Supported Source: CNAView cited source
  13. [13]

    Goldman's prior end-2026 US data-center capacity forecast was 59 GW.

    Derived Supported
  14. [14]

    The Goldman note argues that AI infrastructure investment by major technology firms will likely offset permitting headaches and political barriers, and points to a near-term supply pipeline running through 2027.

    Reported Supported Source: Crypto Briefing summary of Goldman noteView cited source
  15. [15]

    Capacity added during 2027 falls from 36 GW in the prior forecast to 26 GW in the new one, a 10 GW cut of about 28%.

    Derived Supported
  16. [16]

    At most 5 GW of the 10 GW cut to 2027 additions can be projects shifting into 2026; the other 5 GW leaves the end-2027 total.

    Derived Supported
  17. [17]

    Goldman's May demand path implied growth of about 32% in 2026 and 61% in 2027.

    Derived Supported
  18. [18]

    The new forecast implies a 2025 demand base of about 31.6 GW and 2027 demand of roughly 61 GW, about 5 GW below May's 66 GW.

    Derived Supported
  19. [19]

    The 2027 demand increase is 17 GW in the new forecast against 25 GW in May's, 8 GW less.

    Derived Supported
  20. [20]

    The new end-2027 capacity forecast of 90 GW is about 5% below May's roughly 95 GW.

    Derived Supported

Sources

2 independent publishers whose own reporting we read for this story.

  1. channelnewsasia.com

    1 article · October 5, 2026

    Goldman sees US data center growth intact despite opposition
  2. cryptobriefing.com

    1 article · October 5, 2026

    Goldman Sachs forecasts 38% growth in US data-center power demand
  3. mezha.net

    1 article · October 5, 2026

    Goldman Sachs підвищив прогноз потужностей дата-центрів у США на 2026 рік, але знизив оцінку на 2027-й

Topics and entities

Topics